Subsea Pipeline Decommissioning in the Gulf: In Place vs. Removal, Pigging, NORM and the Diver’s Role
Most offshore pipelines in the Gulf are never pulled out. They are cleaned, filled with seawater, cut, plugged and left where they lie. The rules for that are short, the oversight has been criticized, and a federal study of what stays inside the pipe is due to report.
Federal rules allow a pipeline to be decommissioned in place if it is not a hazard to navigation or fishing, does not unduly interfere with other uses and has no adverse environmental effects[1]. The operator must pig it (unless impractical), flush it, fill it with seawater, cut and plug both ends, and bury the ends 3 feet or cover them with concrete mats[2]. GAO found about 18,000 miles, over 97% of decommissioned Gulf pipeline, left on the seafloor, and said BSEE rarely verifies the work[4]. BSEE is now sampling pipelines to see what residue, including NORM, remains after flushing[5].
01. The federal steps, side by side
| Step | Decommission in place | Remove |
|---|---|---|
| Approval | Application with reason, procedures and lengths decommissioned and remaining[2] | Application with procedures, vessel and anchor plans if required, disposal plan, protection of sensitive features and schedule[3] |
| Pigging | Required unless the Regional Supervisor finds it impractical[2] | Same[3] |
| Flushing | Required[2] | Required[3] |
| Fill | Seawater[2] | — |
| Ends | Cut and plug both ends; bury 3 ft or cover with concrete mats[2] | Pipe recovered to a vessel |
| Fittings | Remove valves and fittings that could interfere with other uses[2] | Removed with the line |
| Report | Within 30 days, with a signed certification[6] | Within 30 days[6] |
Summarized from 30 CFR 250.1750–1753. Conditions in each approval can add requirements.
The test for leaving a line in place is in 30 CFR 250.1750: it must not be a hazard to navigation and commercial fishing, must not unduly interfere with other uses of the OCS and must not have adverse environmental effects[1].
02. What happens in practice
Leaving pipe in place is the norm, not the exception. GAO counted about 18,000 miles of decommissioned pipeline, over 97%, left on the Gulf seafloor since the 1960s, compared with about 8,600 miles of active offshore pipeline[4].
- •Little verification. GAO found BSEE does not observe decommissioning, inspect pipelines afterward or verify most evidence submitted, so it cannot be sure lines were properly cleaned[4].
- •Lines move. Hurricanes can shift pipelines long distances, creating hazards for navigation and trawling[4].
- •No money for later removal. GAO noted there is no funding source if a pipeline left in place later needs to come out[4].
- •Rule still pending. GAO’s priority recommendation for updated pipeline rules was open, with BSEE expecting a proposed rule in fall 2026[4].
03. NORM and residue: what stays inside
Flushing does not guarantee a clean pipe. BSEE’s own study notes concern that scale, paraffin, chemicals and naturally occurring radioactive material (NORM) may remain after flushing[5]. NORM in oilfield scale comes mainly from radium that settles out with barium and strontium sulfate from produced water (general industry background).
| BSEE study item | Detail[5] |
|---|---|
| Contractor | CSA Ocean Sciences Inc. |
| Value | $374,570 |
| Period | September 9, 2024 to September 8, 2026 |
| Sampling | At least 10 pipelines and 5 subsea components, offshore and onshore |
| Analysis | Composition and toxicity against USEPA and USCG standards |
| Output | Peer-reviewed public final report |
Status was listed as ongoing on BSEE’s page when checked. We found no published final report as of November 16, 2026.
NORM that is brought ashore falls under state rules. Louisiana publishes a NORM management manual through its Department of Environmental Quality[7]. For crews, the practical point is that any pipe or component recovered to deck may need radiation screening before it is cut, shipped or scrapped (our assessment).
04. Where divers and ROVs fit
| Task | Shelf (diver) | Deepwater (ROV) |
|---|---|---|
| Pig launching and receiving | Topside, with diver help at subsea connections | ROV-operated valves and launchers |
| Cutting the line | Diamond wire, abrasive water jet or hydraulic shears | ROV-deployed cutting tools |
| Plugging the ends | Plugs, blind flanges or grout | ROV-installed plugs |
| Burying or mats | Jetting the end below 3 ft, or placing concrete mats[2] | ROV-guided mat placement |
| Fittings removal | Unbolting or cutting valves and taps[2] | ROV tooling |
| Survey | Visual and probe checks | ROV or AUV survey |
Our general description of methods; each approved application sets the actual procedure.
This is steady shelf work for air and mixed-gas divers, and it grows with the decommissioning backlog described in our decommissioning guide. If BSEE’s study finds significant residue, owners could face more cleaning, more removals or more monitoring (our assessment), any of which adds vessel and dive days.
05. Frequently Asked Questions
Can offshore pipelines be left on the seafloor in the Gulf? ↓
Yes, with approval. Under 30 CFR 250.1750 a pipeline may be decommissioned in place if it is not a hazard to navigation or fishing, does not unduly interfere with other uses and has no adverse environmental effects.
What are the steps to decommission a pipeline in place? ↓
Apply for approval, pig the line unless impractical, flush it, fill it with seawater, cut and plug both ends, bury the ends at least 3 feet or cover them with concrete mats, and remove interfering valves and fittings. A report is due within 30 days.
How much Gulf pipeline has been left in place? ↓
GAO found about 18,000 miles, more than 97% of decommissioned pipeline in the Gulf, left on the seafloor since the 1960s.
Is NORM a problem in decommissioned pipelines? ↓
It may be. BSEE is studying whether scale, paraffin, chemicals and NORM remain after flushing, sampling at least ten pipelines. The final report was not published as of November 2026.
Who does pipeline decommissioning work? ↓
On the shelf, commercial divers cut, plug and bury line ends; in deep water, ROV crews do the same work with remote tooling. Vessels, pigging crews and survey teams support both.
Sources
- [1]30 CFR § 250.1750 — When may I decommission a pipeline in place? (Cornell LII)
- [2]30 CFR § 250.1751 — How do I decommission a pipeline in place? (Cornell LII)
- [3]30 CFR § 250.1752 — How do I remove a pipeline? (Cornell LII)
- [4]U.S. GAO — GAO-21-293, Offshore Oil and Gas: Updated Regulations Needed to Improve Pipeline Oversight and Decommissioning (2021; status updated Mar 2026)
- [5]BSEE — Subsea Infrastructure Decommissioning Study (CSA Ocean Sciences)
- [6]30 CFR § 250.1753 — What must I submit after decommissioning a pipeline? (Cornell LII)
- [7]Louisiana DEQ — Manual for the Management of NORM
All sources accessed November 16, 2026. Figures are as published by each source; agency pages may be revised after publication.
Related
Independent information, not investment, legal or engineering advice. Gulf Coast Subsea is an independent directory. It is not affiliated with or endorsed by any company or agency mentioned on this page. Figures are compiled from public sources and labeled by source and date. Confirm current terms directly with BOEM, BSEE and the companies involved.