Most offshore pipelines in the Gulf are never pulled out. They are cleaned, filled with seawater, cut, plugged and left where they lie. The rules for that are short, the oversight has been criticized, and a federal study of what stays inside the pipe is due to report.

Decommissioned miles left in place ~18,000 (97%+)
Active offshore pipeline ~8,600 miles
Ends buried at least 3 ft
Report due after 30 days
Short answer

Federal rules allow a pipeline to be decommissioned in place if it is not a hazard to navigation or fishing, does not unduly interfere with other uses and has no adverse environmental effects[1]. The operator must pig it (unless impractical), flush it, fill it with seawater, cut and plug both ends, and bury the ends 3 feet or cover them with concrete mats[2]. GAO found about 18,000 miles, over 97% of decommissioned Gulf pipeline, left on the seafloor, and said BSEE rarely verifies the work[4]. BSEE is now sampling pipelines to see what residue, including NORM, remains after flushing[5].

On this page

01. The federal steps, side by side

StepDecommission in placeRemove
ApprovalApplication with reason, procedures and lengths decommissioned and remaining[2]Application with procedures, vessel and anchor plans if required, disposal plan, protection of sensitive features and schedule[3]
PiggingRequired unless the Regional Supervisor finds it impractical[2]Same[3]
FlushingRequired[2]Required[3]
FillSeawater[2]—
EndsCut and plug both ends; bury 3 ft or cover with concrete mats[2]Pipe recovered to a vessel
FittingsRemove valves and fittings that could interfere with other uses[2]Removed with the line
ReportWithin 30 days, with a signed certification[6]Within 30 days[6]

Summarized from 30 CFR 250.1750–1753. Conditions in each approval can add requirements.

The test for leaving a line in place is in 30 CFR 250.1750: it must not be a hazard to navigation and commercial fishing, must not unduly interfere with other uses of the OCS and must not have adverse environmental effects[1].

02. What happens in practice

Leaving pipe in place is the norm, not the exception. GAO counted about 18,000 miles of decommissioned pipeline, over 97%, left on the Gulf seafloor since the 1960s, compared with about 8,600 miles of active offshore pipeline[4].

03. NORM and residue: what stays inside

Flushing does not guarantee a clean pipe. BSEE’s own study notes concern that scale, paraffin, chemicals and naturally occurring radioactive material (NORM) may remain after flushing[5]. NORM in oilfield scale comes mainly from radium that settles out with barium and strontium sulfate from produced water (general industry background).

BSEE study itemDetail[5]
ContractorCSA Ocean Sciences Inc.
Value$374,570
PeriodSeptember 9, 2024 to September 8, 2026
SamplingAt least 10 pipelines and 5 subsea components, offshore and onshore
AnalysisComposition and toxicity against USEPA and USCG standards
OutputPeer-reviewed public final report

Status was listed as ongoing on BSEE’s page when checked. We found no published final report as of November 16, 2026.

NORM that is brought ashore falls under state rules. Louisiana publishes a NORM management manual through its Department of Environmental Quality[7]. For crews, the practical point is that any pipe or component recovered to deck may need radiation screening before it is cut, shipped or scrapped (our assessment).

04. Where divers and ROVs fit

TaskShelf (diver)Deepwater (ROV)
Pig launching and receivingTopside, with diver help at subsea connectionsROV-operated valves and launchers
Cutting the lineDiamond wire, abrasive water jet or hydraulic shearsROV-deployed cutting tools
Plugging the endsPlugs, blind flanges or groutROV-installed plugs
Burying or matsJetting the end below 3 ft, or placing concrete mats[2]ROV-guided mat placement
Fittings removalUnbolting or cutting valves and taps[2]ROV tooling
SurveyVisual and probe checksROV or AUV survey

Our general description of methods; each approved application sets the actual procedure.

This is steady shelf work for air and mixed-gas divers, and it grows with the decommissioning backlog described in our decommissioning guide. If BSEE’s study finds significant residue, owners could face more cleaning, more removals or more monitoring (our assessment), any of which adds vessel and dive days.

05. Frequently Asked Questions

Can offshore pipelines be left on the seafloor in the Gulf? ↓

Yes, with approval. Under 30 CFR 250.1750 a pipeline may be decommissioned in place if it is not a hazard to navigation or fishing, does not unduly interfere with other uses and has no adverse environmental effects.

What are the steps to decommission a pipeline in place? ↓

Apply for approval, pig the line unless impractical, flush it, fill it with seawater, cut and plug both ends, bury the ends at least 3 feet or cover them with concrete mats, and remove interfering valves and fittings. A report is due within 30 days.

How much Gulf pipeline has been left in place? ↓

GAO found about 18,000 miles, more than 97% of decommissioned pipeline in the Gulf, left on the seafloor since the 1960s.

Is NORM a problem in decommissioned pipelines? ↓

It may be. BSEE is studying whether scale, paraffin, chemicals and NORM remain after flushing, sampling at least ten pipelines. The final report was not published as of November 2026.

Who does pipeline decommissioning work? ↓

On the shelf, commercial divers cut, plug and bury line ends; in deep water, ROV crews do the same work with remote tooling. Vessels, pigging crews and survey teams support both.

Sources

  1. [1]30 CFR § 250.1750 — When may I decommission a pipeline in place? (Cornell LII)
  2. [2]30 CFR § 250.1751 — How do I decommission a pipeline in place? (Cornell LII)
  3. [3]30 CFR § 250.1752 — How do I remove a pipeline? (Cornell LII)
  4. [4]U.S. GAO — GAO-21-293, Offshore Oil and Gas: Updated Regulations Needed to Improve Pipeline Oversight and Decommissioning (2021; status updated Mar 2026)
  5. [5]BSEE — Subsea Infrastructure Decommissioning Study (CSA Ocean Sciences)
  6. [6]30 CFR § 250.1753 — What must I submit after decommissioning a pipeline? (Cornell LII)
  7. [7]Louisiana DEQ — Manual for the Management of NORM

All sources accessed November 16, 2026. Figures are as published by each source; agency pages may be revised after publication.

Related

Independent information, not investment, legal or engineering advice. Gulf Coast Subsea is an independent directory. It is not affiliated with or endorsed by any company or agency mentioned on this page. Figures are compiled from public sources and labeled by source and date. Confirm current terms directly with BOEM, BSEE and the companies involved.