Offshore Decommissioning in the Gulf of America (Gulf of Mexico): Idle Iron, Overdue Wells and Who Does the Work (2026)

Since the 1940s, operators have installed more than 55,000 wells and 7,000 platforms on the federal Outer Continental Shelf. Every one of them must eventually be plugged and removed. This guide explains the rules, the size of the backlog, the 2026 policy changes and the subsea work behind each step.

Installed since 1940s 55,000+ wells · 7,000 platforms
Overdue (Jun 2023) 2,700+ wells · 500 platforms
Est. liability $40–70 billion
Bonds held (2023) ~$3.5 billion
Short answer

When a Gulf lease ends, operators generally have one year to plug wells and remove platforms; idle structures on active leases must also be dealt with under BSEE’s idle-iron rules[1][2]. GAO found that, as of June 2023, more than 2,700 wells and 500 platforms – over 75% of end-of-lease and idle infrastructure – were overdue, against an estimated $40–70 billion in total decommissioning cost and about $3.5 billion in supplemental bonds[1]. That backlog is a steady source of plugging, cutting and removal work for Gulf Coast divers, ROV crews and lift vessels.

On this page

01. The rules: when decommissioning is required

Decommissioning on the federal OCS is governed by BSEE’s regulations at 30 CFR Part 250, Subpart Q[3]. Two triggers matter:

Who pays if the operator can’t?
Liability can pass back to earlier lessees and owners. BOEM requires financial assurance (bonds) so that taxpayers are not left with the bill. GAO found BOEM held about $3.5 billion in supplemental bonds as of June 2023 against an estimated $40–70 billion in total decommissioning costs[1].

02. How big is the backlog?

GAO’s 2024 report (GAO-24-106229) is the most recent independent audit of the backlog[1]:

MeasureFigureAs of
Wells installed on the OCS[1]55,000+Since 1940s
Platforms installed[1]7,000+Since 1940s
Overdue wells[1]2,700+June 2023
Overdue platforms[1]500+June 2023
Share of end-of-lease / idle infrastructure overdue[1]Over 75%June 2023
Leases ended 2010–2022 that missed the 1-year deadline[1]40%+ of wells, 50%+ of platforms2010–2022
Estimated total decommissioning cost[1]$40–70 billion2023

GAO figures as published. GAO also found BSEE rarely used civil penalties; its four recommendations to Interior were still open as of March 2026.

For scale: when the idle-iron notice was issued in September 2010, BSEE counted 3,233 idle wells and 617 idle platforms; by February 2013 that had fallen to 2,016 wells and 400 platforms, even as new ones went idle[4]. The backlog shrinks when enforcement is active and grows back as fields age.

03. What changed in 2026

04. The work: what decommissioning looks like underwater

Decommissioning is a sequence of distinct jobs, each with its own crews and equipment:

StepWhat happensSubsea crews involved
Well plugging & abandonment (P&A)Cement plugs set in the wellbore; on subsea wells, done from a rig or intervention vesselROV crews; divers on shallow platform wells
Conductor and casing cuttingCasing strings cut below the mudline, by abrasive water jet, diamond wire or explosivesAir and mixed-gas divers, ROV tooling
Topsides removalDeck and equipment lifted off in one piece or in sectionsHeavy-lift and derrick barges
Jacket removalLegs severed below the mudline, jacket lifted or towedDivers, ROV, explosives contractors
Pipeline decommissioningLines flushed, cleaned, plugged and often left in place where approvedDivers on the shelf; ROV in deepwater
Site clearanceSeabed survey to confirm debris is goneSurvey vessels, ROV

General description for orientation; actual methods are set in each BSEE-approved decommissioning application.

Much of this work is on the continental shelf (30–200 m), where air and mixed-gas divers still do cutting and rigging. That is why decommissioning sits alongside pipelay in our 3D map’s shelf sector, and why Louisiana dive companies list P&A and removal among their core services. For pay context see commercial diver salary in Louisiana and Texas.

Rigs-to-Reefs
Instead of hauling a jacket to shore, an operator can, with approval, topple it or tow it to a designated artificial-reef site. Texas and Louisiana run state artificial reef programs, and BSEE oversees the federal side of the Rigs-to-Reefs process[4].

05. Outlook for crews and contractors

06. Frequently Asked Questions

How long do operators have to decommission in the Gulf of America? ↓

Generally one year after a lease ends. Under BSEE's idle-iron rules, idle wells on active leases must be addressed within three years and idle platforms removed within five years of no longer being useful.

How many offshore wells and platforms are overdue for decommissioning? ↓

GAO reported that as of June 2023 more than 2,700 wells and 500 platforms in Gulf federal waters were overdue - over 75% of end-of-lease and idle infrastructure.

How much will Gulf decommissioning cost? ↓

GAO cited estimates of $40 to $70 billion in total decommissioning costs, against about $3.5 billion in supplemental bonds held by BOEM as of June 2023.

What is idle iron? ↓

Idle iron is offshore infrastructure - wells, platforms and pipelines - that is no longer producing or useful for operations but has not been plugged or removed.

Do commercial divers work on decommissioning? ↓

Yes, especially on the continental shelf, where air and mixed-gas divers cut conductors and jacket legs, rig lifts and decommission pipelines. Deepwater subsea wells rely mostly on ROVs and intervention vessels.

Sources

  1. [1]U.S. GAO — GAO-24-106229, Offshore Oil and Gas: Interior Needs to Improve Decommissioning Enforcement (Jan 2024)
  2. [2]BSEE — NTL 2010-G05, Decommissioning Guidance for Wells and Platforms (idle iron)
  3. [3]eCFR — 30 CFR Part 250 Subpart Q, Decommissioning Activities
  4. [4]Offshore Engineer — BSEE: Offshore decommissioning accelerates in Gulf of Mexico (2013 data)
  5. [5]Mondaq — BOEM proposes to loosen supplemental financial assurance requirements (2026)
  6. [6]Sen. Peter Welch — Bicameral bill to decommission offshore wells, platforms and pipelines (Mar 2026)
  7. [7]Federal Register — Restoration of names: Gulf of America (BSEE, Sept 15, 2025)

All sources accessed November 1, 2026. Figures are as published by each source; agency pages may be revised after publication.

Related

Independent information, not investment, legal or engineering advice. Gulf Coast Subsea is an independent directory. It is not affiliated with or endorsed by any company or agency mentioned on this page. Figures are compiled from public sources and labeled by source and date. Confirm current terms directly with BOEM, BSEE and the companies involved.